South Okanagan Secondary School
Project Schedule

September 20, 2009~~~   
SD approval to commence construction documents

February/March 2010~T   
Tender and award SOSS construction contract

PHASE 1A~Summer~2010~~~
~(2 months) -~partial demolition [tip of the west wing]

PHASE 1B April 2010 to June~2011~~~~~~~~
(14 months) - new services~and new building construction [this would include the Science/ Multi-purpose, Gym additions], West Gym renovations

PHASE 2~ May 2011 to July, 2012~~~~~~~~~~
(14 months) - move into new, demo remainder of west wing, add portables~and renovate~~~~~~~~ shop~building~through summer 2011, renovate existing [auditorium, east and south] wings

PHASE 3 April 2012 to August 2012~~~~
(4 months) - complete site works [including parking lots, courtyard]; start with east parking lot, finish with south parking lot

KMBR Architects Planners Inc. + Bevanda Architecture Inc.


Floor Plans
SOSS New Construction.jpg
SOSS elevations New Construction.jpg

SOSS Basement Plan.jpg
SOSS Main Floor Plan.jpg
SOSS second floor plan.jpg
Exterior View.jpg
SOSS Tec ed renovation.jpg

Aerial view of Courtyard.jpg
Exterior Courtyard View2.jpg
Exterior Courtyard View.jpg
SOSS view through Library.jpg
SOSS view through Library2.jpg
SOSS view through Library3.jpg
SOSS view through Library4.jpg
Exterior View of New Library (existing Gym).jpg
SOSS interior view of Theatre2.jpg
SOSS interior view of Theatre.jpg
SOSS interior view of Multi Purpose Room.jpg
View of Multi Purpose Room Structure.jpg


School District 53