South Okanagan Secondary School
Project Schedule
September 20, 2009~~~
SD approval to commence construction documents
February/March 2010~T
Tender and award SOSS construction contract
PHASE 1A~Summer~2010~~~
~(2 months) -~partial demolition [tip of the west wing]
PHASE 1B April 2010 to June~2011~~~~~~~~
(14 months) - new services~and new building construction [this would include the Science/ Multi-purpose, Gym additions], West Gym renovations
PHASE 2~ May 2011 to July, 2012~~~~~~~~~~
(14 months) - move into new, demo remainder of west wing, add portables~and renovate~~~~~~~~ shop~building~through summer 2011, renovate existing [auditorium, east and south] wings
PHASE 3 April 2012 to August 2012~~~~
(4 months) - complete site works [including parking lots, courtyard]; start with east parking lot, finish with south parking lot
KMBR Architects Planners Inc. + Bevanda Architecture Inc.